Sizewell A turbine hall demolition marks major step in site restoration
A significant demolition milestone has been reached at the Sizewell A nuclear site on the Suffolk coast, where an area the size of a professional football pitch has been cleared, de-planted, and demolished to prepare for the next phase of site restoration.
The project featured the largest-ever use of explosives on a UK nuclear site and the longest programmed detonation sequence in Europe, targeting four massive concrete plinths supporting two 650-tonne turbogenerators.
This approach reduced the demolition schedule by four months, cut costs by £300,000, and minimized vibration impact compared to conventional mechanical removal techniques. The use of explosives also reduced CO2 emissions by approximately 40 tonnes by lowering fuel consumption from heavy machinery.
Over 17,000 tonnes of concrete and rubble were removed from the turbine hall, fire station, and electrical annexe — more than the weight of the six million bricks used in Battersea Power Station. The material was processed through a mobile crusher to produce reusable aggregate, enabling export and recycling.
Two overhead cranes, each with a 90-tonne safe working load and weighing 65 tonnes, were extracted from their rails and moved to a landing pad for metal recycling.
In total, 11,000 tonnes of scrap metal have been recovered, generating over £3 million to offset decommissioning costs. The project achieved a 95% recovery rate for construction and demolition waste, significantly above industry averages, reflecting strong sustainability goals.
Alan Walker, Sizewell A Site Director, said:
“This is an incredible achievement for NRS, our contract partners Erith, the Office for Nuclear Regulation (ONR) and the Nuclear Decommissioning Authority (NDA).
I would like to thank everyone including those involved and our neighbours for their continued support throughout, as well as the ONR for enabling us to push the boundaries of innovation in conventional demolition together. The learning from this will be applied to other NRS projects to continue delivering efficient, value for money decommissioning and restoration of nuclear sites.”
David Rushton, NDA Programme Manager, noted the demolition’s significance in reshaping the Sizewell A skyline and supporting the NDA’s sustainability targets through material reuse.
Andrew Bull, ONR’s Nominated Site Inspector at Sizewell A, highlighted the close working relationship with NRS, enabling a modern and sometimes groundbreaking approach to accelerate dismantling safely and cost-effectively.