Scaffolding Excellence Awards 2026: VRAS Headhouse Encapsulation Scaffold – CCS Scaffolding Ltd
CCS Scaffolding Ltd was appointed to design and deliver a fully encapsulated scaffold at the Victoria Road Auxiliary Shaft (VRAS) Headhouse in North Acton, London. The scaffold needed to keep a specialist fire protection membrane dry while it cured on the headhouse steelwork.
Previous encapsulation arrangements elsewhere on the project had allowed water ingress to affect the fireproofing process so at VRAS the challenge was to remove that risk without restricting the access routes required by other trades. Following delays outside of our control we were left with less than four weeks remaining before the fireproofing contractor was due to mobilise.
A conventional independent scaffold structure would have occupied valuable space around the headhouse that was required for progression of works so we worked with the client and our design partners to develop a bespoke roof mounted cantilever system which saw cantilevered beam sections projected from the roof and then utilising cables to create a fully weatherproof enclosure.
“The big thing was keeping everyone moving,” says Project Manager Hayden Howell, “The fireproofing needed protection without getting in the way of the other trades.”
The system kept operational areas clear while other trades continued working in and around the structure by sequencing the installation. Beams were assembled in pairs at ground level and craned into position, reducing both working at height and manual handling.
The roof slab permitted ties to a depth of 60mm max. so a high density anchoring arrangement was used with approximately 100 anchors were each double fixed into the slab with pull out testing and load checks being carried out to verify the loads.
The original design was based on 25mph wind loading but site conditions immediately demanded a more robust solution so the design was revised with the client and designer to accommodate 50mph gusts instead with additional sheeting cables installed and updated calculations introduced without affecting site progress or planned completion.
Controlled flexibility in the cable system allowed movement from wind to be absorbed without transferring excessive forces into the structure or roof anchors however when potential movement was identified in the cantilever beams during high winds and operations were paused for further engineering review and load checks. “We weren’t just going to crack on and hope for the best,” says Project Supervisor Cameron Howell, “We stopped, brought the designers to site and then installed additional bracing and supporting standards to the roof structure.” Inspections were also increased to twice weekly with added focus on cable tension, beam movement and encapsulation condition.
Despite delayed mobilisation, weather disruption and engineering challenges, the scaffold enclosure was completed and handed over on time with no safety incidents and allowing fireproofing to begin on schedule.
Compared with a conventional temporary roof scaffold, this scheme reduced the ground level footprint of the enclosure and demonstrated the value of treating scaffolding as an engineered part of the wider construction strategy, with the solution shaped around the building, programme, environmental conditions and the needs of the stakeholders.