McLaughlin & Harvey breaks ground on National Grid control entre
McLaughlin & Harvey has begun work on National Grid’s new Electricity Transmission Control Centre (ETCC), a major project designed to strengthen the resilience of Great Britain’s high-voltage network as it expands to meet rising energy demands.
The facility is being built at Hams Hall in the Midlands on the site of a decommissioned 275kV substation. The project will consolidate multiple control functions into a single purpose-built space, enabling more efficient management of the country’s growing transmission network.
The UK’s electricity grid is undergoing rapid expansion as new renewable generation comes online and energy demand patterns shift. The ETCC will operate alongside National Grid’s existing Transmission Network Control Centre, running 24/7 to manage the flow of power across England and Wales.
Key Construction Milestones
McLaughlin & Harvey started on site in April 2025 with groundworks and piling completed by July. Steelwork is now underway, marking a significant stage in the build programme. The control centre is scheduled to be fully operational in 2028.
The project is redeveloping a brownfield site with sustainability in mind, aiming to minimise embodied carbon during construction and deliver a 10% biodiversity net gain.
Local and Sector Impact
Once complete, the ETCC will accommodate hundreds of engineering roles, supporting the skilled workforce needed to operate an increasingly complex transmission system. The redevelopment is also expected to create construction jobs throughout the build phase and provide STEM education opportunities for the local community.
As part of the wider works, National Grid’s Community Grant Programme will make up to £20,000 available for local organisations and charities.
Industry Collaboration
Paul Griffen, Managing Director at McLaughlin & Harvey, and Jon Davies, Director of Network Operations and Intelligence at National Grid, marked the start of the steelwork phase by signing a beam on site.
Griffen said the project highlights the scale and complexity of delivering critical infrastructure:
“Projects like this demonstrate the expertise required to deliver high-specification, technically demanding facilities that will serve the UK for decades.”
Davies said the ETCC represents a step-change in how the grid is managed:
“The facility will futureproof our grid’s resilience and ensure we have the people and technology in place to keep power flowing as the energy transition gathers pace.”