Mainmark completes ground improvement works at Tottenham Hale Station
Specialist ground engineering contractor Mainmark UK has completed ground improvement works at Tottenham Hale Station as part of a wider refurbishment programme.
The £150,000-plus package involved strengthening ground beneath 77 new foundation locations for replacement platforms at the busy North London transport interchange.
Tottenham Hale Station serves National Rail’s Greater Anglia and Stansted Express services, alongside the London Underground Victoria line.
Ground strengthened for new station platforms
Platforms 3 and 4, which were constructed from precast concrete, had deteriorated, with concerns over the condition of supporting structures beneath them and their long-term stability.
READ MORE: McLaughlin & Harvey wins £70m Holborn Circus contract

Temporary supports had previously been installed to mitigate the risk of collapse before plans were developed to replace the platforms with glass-reinforced polymer (GRP) structures designed to require less maintenance.
The existing ground beneath the proposed new foundation locations also required improvement to provide suitable support for the replacement platforms.
Working for CML, a Tier One Principal Contractor for Network Rail and other infrastructure clients, Mainmark used its Teretek engineered resin injection system to strengthen the ground without excavation.
The works targeted ground to a depth of two metres beneath each foundation location. Resin was injected through small-diameter access points to densify variable made ground and granular soils.
The approach allowed the works to be completed within three shifts, with minimal disruption to the wider station refurbishment programme.
READ MORE: Government to set out construction workforce plan later this year
David Hedley, Infrastructure Lead at Mainmark UK, said: “The successful delivery at Tottenham Hale Station demonstrates how engineered resin injection can deliver precise, measurable ground improvement under extreme time and environmental constraints, supporting modern rail upgrades without compromising programme or performance.”
Works completed within rail possession window
The ground improvement package had to be delivered within tightly controlled rail possession windows, while multiple contractors were working simultaneously across the station site.
Raj Sharma, Contracts Manager at CML, said: “Mainmark UK demonstrated a high level of technical expertise and professionalism during the platform foundation works at Tottenham Hale Station. Their ability to deliver safely, on programme, and with minimal disruption under challenging conditions was critical to the project’s success. We would gladly engage Mainmark UK on future works.”
The ground engineering package forms part of the wider refurbishment of Tottenham Hale Station, with the replacement platforms intended to address the deterioration of the existing structures.
The project also highlights the use of non-excavation ground improvement techniques on live and constrained rail infrastructure, where maintaining access and limiting disruption can be critical to programme delivery.