HS2 Ltd completes central structure of Wendover green tunnel

By Published On: October 23rd, 2026Categories: News, Top Stories

HS2 has completed the central structure of its 1.4km cut-and-cover green tunnel at Wendover in Buckinghamshire, bringing the project a step closer to reconnecting the railway with the surrounding countryside.

The tunnel is being built in a cutting alongside the A413, west of Wendover, to reduce noise and disturbance for nearby residents. Once construction is complete, earth will cover the structure to help integrate the railway into the landscape.

The central structure was completed this week when the final precast concrete segment was installed on Monday, joining the two halves of the tunnel for the first time.

READ MORE: FMB warns £876m of Scottish home improvement work is delayed

Hs2

HS2 Ltd’s project manager, Umesh Gorasia, said: “It’s great to see the two halves of the tunnel linked up for the first time. Once complete, the green tunnel will dramatically reduce disruption from passing trains and blend the railway into the countryside.

“There’s still some way to go, but we’re making good progress and I’d like to thank the team for all their hard work.”

More than 2,000 concrete segments installed

The Wendover tunnel is being constructed from precast concrete segments arranged in an M-shaped structure, with separate sections for northbound and southbound trains.

Construction began with the installation of the first segment in spring 2025. Since then, contractor EKFB has installed more than 2,000 segments to complete the central structure, with the work carried out across two sections to allow excavation, construction and backfilling to progress simultaneously.

EKFB project manager Elton Qafaliaj said: “EKFB installed the first concrete segment in spring 2025, and in less than 18 months, we have lifted more than 2,000 segments to complete the central structure of the Wendover green tunnel. This was a huge undertaking and has required the expertise of a skilled workforce. The team has worked together to safely overcome challenges, keeping productivity high and pushing the construction programme forward.

“Seeing the two halves of tunnel finally come together was a proud moment for everyone involved.”

READ MORE: United Infrastructure joins BEAMA amid £181bn network investment plan

More than 1.2 million cubic metres of material, mainly chalk, was excavated to create the level base for the tunnel. The material was stored on site and is now being returned and compacted above the structure to distribute the weight evenly.

Most of the concrete segments were lifted into position using cranes. However, those beneath the temporary bridge carrying Ellesborough Road over the construction site required a different approach.

A self-propelled modular transporter (SPMT), supported by 16 sets of wheels, was used to lift the segments from underneath and position them precisely beneath the bridge.

Portal works and landscaping next

With the central structure in place, work will focus on the portals at either end, completing the floor slab and carrying out the internal fit-out.

Ellesborough Road, which connects Wendover with the direction of Princes Risborough, currently crosses the construction site on a temporary bridge. The final stage will involve realigning the road over the completed tunnel and finishing the landscaping.

EKFB is the main works contractor for HS2’s central section through Buckinghamshire and into South Warwickshire. The joint venture comprises Eiffage, Kier, Ferrovial Construction and BAM Nuttall.

READ MORE: Government unveils £625m Construction Jobs Plan

Wendover is one of three green tunnels being built by EKFB. The contractor is sharing construction lessons across the projects to improve productivity and accelerate delivery. Measures include prefabricating reinforcement cages for the base slab, improving concrete deliveries through the tunnels and testing whether larger machinery can safely be used for backfilling.

The Wendover structure is one of five cut-and-cover green tunnels planned along HS2 between London and Birmingham. The Copthall tunnel, on the outskirts of London, was completed in summer 2026. The other tunnels are at Chipping Warden, Greatworth and Burton Green.

Across the route, approximately 65 miles (105km) of tunnels are planned, with 130 million tonnes of earth due to be excavated. Most tunnels will be deep-bored, while the five green tunnels will be constructed using the cut-and-cover method.

HS2 is intended to improve connections between London and Birmingham and free up capacity for more local services on the congested southern section of the existing West Coast Main Line into London Euston.

However, significant construction work remains across the 140-mile route, with HS2 Ltd chief executive Mark Wild leading a comprehensive reset of the project to improve delivery efficiency and reduce costs.