Developers warned over Building Safety Levy delays ahead of October deadline

By Published On: May 22nd, 2026Categories: Uncategorized
Developers could face additional project costs and programme delays if they fail to prepare for the introduction of the Building Safety Levy before its October 1 implementation date, according to Pick Everard.

The levy, which forms part of the government’s post-Grenfell building safety reforms, will apply to new residential developments through an upfront statutory charge linked to building control applications submitted from October 1 onwards.

Industry specialists have warned that developers expecting to submit schemes before the deadline may underestimate the time required to reach technical design stage and secure compliant building control applications.

READ MORE: Plan your day at Build North Expo!

That could leave some projects exposed to unexpected levy costs if applications are delayed or rejected.

Gateway 2 building safety approvals may create programme risks for developers

The warning is particularly relevant for higher-risk residential buildings progressing through the Gateway 2 approval process under the Building Safety Act regime.

Under the system, projects requiring resubmission following refusal could face significant programme disruption, particularly given the additional scrutiny now applied to building regulations compliance.

Vaso Vaina, Building Safety Act associate at Pick Everard said developers should review project readiness urgently.

“Considering the effects of the Building Safety Levy on projects now will result in better quality applications, for a better likelihood of a successful pre-deadline submission,” she said.

READ MORE: Cameron Homes secures approval for 119-home Uttoxeter redevelopment 

“Projects that will not be ready for submission before October 1 must factor the Building Safety Levy into viability appraisals, and the allocation of levy risk should be given careful consideration.”

The levy will be collected by local authorities regardless of which building control route is used. Applicants will need to submit levy-related information, including residential unit numbers and planning references, when lodging applications.

Councils are expected to issue Levy Liability Notices within five to eight weeks, although charges could later be recalculated if schemes change during delivery.

Construction sector questions impact of levy on housing viability and delivery

The levy is intended to help fund the remediation of unsafe residential buildings following the Grenfell Tower fire, but concerns remain across the construction sector about its cumulative impact on housing viability and project delivery.

Developers are already facing rising build costs, tighter funding conditions and more complex regulatory approval processes under the Building Safety Act framework.

READ MORE: Build North Expo: One month to go!

Some industry observers have argued that additional upfront charges and extended approval timelines risk slowing housing delivery, particularly on marginal schemes outside London where profit margins are often tighter.

Vaina said uncertainty around compliance and administration could create further pressure for project teams.

“It is vital that developers seek clarity and support to navigate the levy if they are only just starting to consider its implications,” she said.

“The upcoming implementation of the levy may introduce some uncertainty into projects when considering time and resources. Early compliance planning resulting in robust building control applications are the most effective ways to address these risks.”

She added: “The levy can have an impact on everything from cash flow to project viability.

“Failing to plan for this additional tax or the potential effects of administrative delays, could prove particularly damaging. In what is an economically challenging landscape for construction at the moment, early engagement is the key to mitigating delivery risk and additional cost exposure, helping to stormproof project delivery as much as possible.”