Barhale completes second phase of Victoria trunk upgrade

By Published On: August 5th, 2026Categories: News, Top Stories

Barhale has completed the second phase of Thames Water’s Victoria trunk main rehabilitation programme, delivering more than 500 metres of upgraded water infrastructure to improve network resilience and reduce flood risk in central London.

The project follows the successful completion of Phase 1, which focused on replacing sections of the strategic water main around Victoria Station.

Phase 2 extended rehabilitation works further along the network, targeting ageing cast iron infrastructure in an area where failures could result in significant flooding to surrounding properties.

The scheme involved installing more than 500 metres of polyethylene (PE) barrier pipe within an existing 30-inch cast iron trunk main using sliplining techniques, with open-cut excavations limited to launch pits, reception pits and connection points.

READ MORE: Construction begins on 48 affordable homes to tackle Cornwall housing demand

Barhale

Barhale

Before installation, the existing pipeline was cleaned, scraped and surveyed to ensure it was suitable for rehabilitation.

The project also included the replacement of hydrants, valves and cross connections, alongside enabling works including under-pressure valve installations, non-destructive testing (NDT), CCTV inspections, LiDAR surveys and flow management to maintain water quality throughout the programme.

Construction team overcomes complex central London constraints

Working in one of London’s busiest urban environments presented significant engineering and logistical challenges.

The route passed through Westminster and the Royal Borough of Kensington and Chelsea, requiring close coordination with local authorities while navigating heavily congested streets, existing underground utilities, residential properties, embassies and commercial premises.

Barhale also worked alongside contractor GSM, which was installing fibre optic ducting along the same route. Both teams coordinated construction activities and sequencing to minimise disruption and maintain programme delivery.

Engineering redesign keeps project on schedule

During construction, the project team encountered a major technical challenge after a planned line-stop installation proved impossible because of surrounding underground services.

READ MORE: Stonewater completes 30 Passivhaus homes in Somerset

The issue required a redesign of the construction methodology and approximately two months of reprogramming before an alternative solution could be agreed.

With central London’s annual festive street works embargo approaching, Barhale worked with Kensington and Chelsea Council to develop an accelerated delivery programme.

The revised approach included opening additional work fronts, introducing Saturday working and resequencing construction activities to complete critical sections before restrictions came into force.

The contractor also converted approximately 50 to 60 metres of planned open-cut installation to sliplining, reducing excavation requirements, lowering embodied carbon and minimising disruption to residents.

Community engagement maintained throughout construction

Throughout the project, Barhale maintained regular communication with residents through weekly engagement and advance notification of planned works.

READ MORE: Lovell launches £42m South East Coalville housing development

Access to homes was maintained throughout construction, while the contractor also engaged directly with local embassies to accommodate operational requirements.

The completed scheme strengthens the resilience of Thames Water’s strategic network, reducing the risk of trunk main failures and flooding while improving the reliability of water supplies serving the Putney supply zone.